Wet Start To October Delays Highway 30 Bridge Construction Near Grand Junction

The Iowa Department of Transportation has reported that the heavy rainfall seen throughout the beginning of October has delayed the completion of the Highway 30 bridge replacement project near Grand Junction. The project, which was scheduled to be completed by the end of this month, has so far been delayed about a full week. The new completion estimate is now falling within the first week of November. Crews will begin pouring the 44-foot wide bridge this week. The nearly $7 million project started in April of this year.